Churchfield Road, Houghton Regis

This scheme was carried out on behalf of Ringway Jacob.

It was a long scheme that last for 8 weeks. Running from 8th August to 29th September.

Works carried out involved resetting Vehicle Cross Over points, replacing broken kerbs. There was also 3,600 m2 of footpath to excavate and relay with 20mm binder and a 6mm surface course totaling an amount of  just under 860 tonnes of asphalt.