Emergency Works Carried Out On A428

Thanks to all employees at DJT Surfacing Ltd that help organise & resurface the carriageway yesterday afternoon on the A428 by Kempston, Bedfordshire. After an accident this morning which a lorry overturned which caused an oil spillage that damaged the carriageway. We got a call at 13.00pm by Bedford Borough Council asking if we could help carry out emergency works to be completed by 17.00 hrs.

The area was planed off at 50mm deep and 16 tonne of  10mm SMA was laid.

Fantastic teamwork to get an urgent matter resolved and a big congratulations to everyone involved.