Sevenoaks Hospital

This scheme took 15 visits to complete from December 2017 to April 2018.

It was a full car park reconstructions. This included various disciplines

  • Taking up the existing car park surface and subbase, 
  • Installing minor drainage,
  • Laying a new type 1 subbase, 
  • Laying binder and asphalt surface,
  • Road Markings, (Carried out by Coutts)
  • Installing fencing.