Well Street, Buckingham

A very difficult but rewarding job.

Carried out on behalf of Ringway Jacob in Buckinghamshire.

Duration of the Scheme was 7 days.

The project was to rejuvenate the ally way for the residents.  This involved excavating old failed concrete and bringing out the hardcore with wheel barrows. Laying a new sub base, then finally proceeded to pave approx. 80m2.

The finished product was received with high praise from residents and the client for all of those involved.