Woolgrove School, Letchworth

Works undertaken in the Summer Holidays to keep disruption down to a minimum

The scheme consisted of planing out various patches with our own 0.5m planer.

Adjust ironworks that were in the patches.

Regulated any areas with AC20mm binder course, then proceeded to overlay with 6mm SMA surface course. In total 138 tonne was laid with our paving machine

Lining was carried out by John Coutts.

The projected last 2 days.